36102 090203
TROUBLESHOOTING
A troubleshooting guide is provided to suggest probable causes and remedies for the most likely problems
encountered. If the problem remains after exhausting the troubleshooting steps, contact the Bunn-O-Matic
Technical Service Department.
Inspection, testing, and repair of electrical equipment should be performed only by qualified service personnel.
All electronic components have 120 volt ac and low voltage dc potential on their terminals. Shorting of
terminals or the application of external voltages may result in board failure.
Intermittent operation of electronic circuit boards is unlikely. Board failure will normally be permanent. If an
intermittent condition is encountered, the cause will likely be a switch contact or a loose connection at a
terminal or crimp.
Solenoid removal requires interrupting the water supply to the valve. Damage may result if solenoids are
energized for more than ten minutes without a supply of water.
The use of two wrenches is recommended whenever plumbing fittings are tightened or loosened. This will help
to avoid twists and kinks in the tubing.
Make certain that all plumbing connections are sealed and electrical connections tight and isolated.
This brewer is heated at all times. Keep away from combustibles.
WARNING Exercise extreme caution when servicing electrical equipment.
Unplug the brewer when servicing, except when electrical tests are specified.
Follow recommended service procedures
Replace all protective shields or safety notices
PROBLEM
Brew cycle will not start
PROBABLE CAUSE
1. No water
2. No power or incorrect voltage to
the brewer
3. ON/OFF Switch
4. Start Switch
REMEDY
Water lines and valves to the brewer
must be open.
(A1) Check the terminal block for
120 volts across the black and
white terminals on two wire 120
volt brewers.
(A2) Check the terminal block for
120 volts ac across the red and
white and the black and white ter-
minals on 120/208V and 120/240V
volt brewers.
(B) Check circuit breakers or fuses.
Refer to
Service
- ON/OFF Switch
for testing. See page 18
Refer to
Service
- Start Switch for
testing procedures. See page 20