Wall unit mounting - Fig. 7
• Mark the wall with a centre line, this will aid mounting procedure (1),
position the template so that the mid line printed on the template
matches with the centre line previously drawn, the lower side of the
template corresponds to the lower side of the hood once mounted
(2).
• Drill four holes Ø 8mm and fit four wall plugs (3).
• Drill two holes Ø 8mm on the upper side close to the ceilling (4) use
the chimney support as a template, check that the mid of the
chimney support corresponds to the mid of the centre line
previously drawn, fit two wall plugs.
Note: ONLY in case the hood is to be used in filter version, mount
the deflector E on the chimney support and the connection flange G
with two screws each (5).
• Fix the chimney support onto the wall with two screws and washers
(6).
• Hang the hood (7), remove the grease filters and fix it definitively
with two screws and washers (8), check that all four screws are
securely tightened.
• Fit an exhausting pipe (9) to connect the outlet hole D of the hood to
the connection flange G of the deflector E (Filter version) or to the
outside (Extractor version).
• Make electrical connection (10), but leave the hood disconnected
from the mains supply.
• Fix the circuit board and connection block unit on the top side of the
hood with two screws (boxes facing frontwards) (11).
• Place the cable clamp in the corresponding housing (12).
• Position the chimney and secure them in place, first up (13a) to the
chimney support (13b) , then slide it downwards making sure the
cable clamp (step 12) is seated in the housing on chimeny (14) and
that the control buttons match with the corresponding openings
(15).
• Adjust the position of the push-button box using two screws from
the inside of the motor housing (16).
• Fix the lower section of the chimney with two screws from the inside
of the hood (17).
• Refit the grease filters, connect the hood the the home general