6
Instruction for the Installer
The following instructions about installation
and maintenance must be carried out by
qualified personnel in compliance with the
regulation in force.
The appliance must be electrically
disconnected before all interventions. If any
electric supply to the appliance is required to
carry out the work, ensure all the necessary
precautions are followed.
The side walls of the unit in which the hob is
going to be installed, must not exceed the
height of the working top.
Avoid installing the appliance in the proximity
of inflammable materials (e.g. curtains, tea
towels etc.).
Gas connection
If using flexible metallic pipes, be careful they do not
come in contact with mobile parts or they are not
squeezed. Use the same attention when the hob is
combinated with an oven.
This hob is set to operate with natural gas with nominal
pressure of 20 mbar. No regulation is required for use by
this type of gas.
IMPORTANT - To ensure a correct operation, a saving
of energy and the long-life of the appliance, the voltage
pressure of the appliance must correspond to the
recommended values.
A) Ramp with ending nut
B) Washer
C) Adjustable connection
Fig. 2
FO 2365
Gas Burners Rating
Rapid Burner (big) 3,0 kW (G20) - 2,8 kW (G30/G31)
Auxiliary Burner (small) 1,0 kW
Class 3 Appliance
Category II2H3B/P
Setting Natural Gas G20 - 20 mbar
Gas connection G 1/2"
Electric Supply 230 V 50 Hz
Hob recess dimensions
Length 270 mm.
Width 490 mm.
This appliance complies with the following
E.E.C. Directives:
- 73/23 - 90/683 (Low Voltage Directive);
- 89/336
(Electromagnetical Compatibility Directive);
- 90/396 (Gas Appliances)
- 93/68 (General Directives)
and subsequent modifications.
Technical Data
Before fitting the appliance ensure that the installation
has the correct voltage for the appliance. At full capacity,
the drop in pressure must not exceed 5%. Such a drop in
pressure is caused by the following parameters:
- maximum capacity of meter;
- diameter and lenght of the tube in front and behind the
meter;
- section of transit of variuos tubes positioned on the
circuit;
- diameter of eventual connections.
The adjustable connection is fixed to the comprehensive
ramp by means of a threaded nut G 1/2". Insert the
supplied washer between the ramp and the adjustable
connection.
IMPORTANT - When the final connection has been
made, it is essential that a thorough leak test is carried
out on the hob and installation. Use some soapy water,
never a flame.