Henny Penny SCR-6/8 Convection Oven User Manual


 
SCR-6/8
2-6. CONTACTOR
(Continued)
6. Check voltage as follows:
Test Points Results
from terminal 29 to 28 The voltage
from terminal 27 to 28 should read the
from terminal 27 to 29 same at each terminal.
If contactor proves defective:
7. Remove the four screws securing the contactor to the
bracket and remove contactor.
8. Install new contactor, replace wires, and replace side
Step 7 panel.
9. Restore power to unit.
2-7. DRIVE MOTOR
REPLACEMENT KIT 1. Remove electrical power to unit.
To avoid electrical shock or property damage, move
the power switch to OFF and disconnect main circuit
breaker, or unplug cord at wall receptacle.
2. Remove rod and discs from unit. (See Cleaning Section of
the Operator’s Manual.)
3. From the control side of the unit, remove the right side
panel.
4. Cut the three wires from the motor.
5. Using 9/16" socket, remove the bolts securing the
Step 5 motor to the bracket, and pull motor from unit.
1207 2-5
Replacement:
Step 4