Hotpoint HDI90X Ventilation Hood User Manual


 
7GB
INSTALLATION
FIXING THE FRAME
Before fixing, seperate the Upper section 2.1 and
the Lower section 2.2 from the frame by unscrewing
the screws 12c. Then seperate the two sections of
the frame (Upper and Lower) by unscrewing the 8
side screws.
Fix the Fixing Part of the Upper Chimney 26 to the
hanging kit using the 2 screws 12w (M3 x 8).
Upper Frame
Align the power supply cable feed hole.
Fix the upper frame to the ceiling of shelf using:
For concrete ceilings, use the appropriate plugs for the screw size (not provided).
For hollow brick ceilings of wall thickness of approximately 20mm: use 4 plugs 11 and 4
screws 12h (5.2 x 70), provided.
For wooden beam ceilings, use 4 wood srews (not provided).
For wooden shelf, use 4 screws 12g (M6 x 80) with washers 22 and nuts 23, provided.
Lower Frame
Fix the lower frame using the 8 previously removed screws, adjusting the length according to the
installation height (hood body lower fixing surface must be at least 710mm from the hob).
For the recirculation version, turn the frame in the direction chosen for the recirculated air outlet.
The frame mounting must be secure to withstand the weight of the hood and any stresses caused
by the occassional side thrust applied to the device. On completion, check that the base is stable,
even if the frame is subjected to bending.
In all cases where the ceiling is not strong enough at the suspension point, the installer must
provide strengthening, using suitable plates and backing pieces anchored to the structurally sound
parts.