KitchenAid,
VALUE DISPOSERS
MODELS KWC=200B, KD-200
KD-100
INSTALLATION INSTRUCTIONS
INSTALLER: FINAL CHECK LIST
GE.RlcL
emove unit from carton and check for shipping damage.
0 2. Sink flange assembled in center of drain opening and tightly sealed.
0 3. Disposer level - not installed at an angle.
0 4. If a dishwasher drain is connected into the disposer, check to assure that
the inlet knockout has been removed.
PLUMBING
0 1. If installed in old house, existing drain line from sink to sewer cleaned.
0 2. Long, horizontal drain lines eliminated.
0 3. Drum traps and grease traps should not be used.
0 4. Seal at drain spout properly positioned.
0 5. Center line height of drain line must not exceed center line height of
disposer discharge opening.
0 6. M oun mg screws and spout screws properly tightened to prevent leaks. t’
0 7. Compliance with all aspects of local plumbing code.
ELECTRICAL CONNECTION
0 1. Properly fused, 115 volt, 60 hertz branch circuit of 15 ampere capacity.
0 2. Disposer properly grounded before operating.
0 3. All connections must comply with the National Electrical Code and/or
local electrical code.
OPERATIONAL
0 1. Before operating, check to assure grind chamber is free of any foreign
objects.
0 2. Activate disposer -test for grinding performance and water leaks.
THANK YOU INSTALLER:
1. Complete Installation Check List.
2. Leave all literature (including Check List) for customer.
3. Notify dealer that electrical work and plumbing are completed.