Southbend SB-5-ES Oven User Manual


 
OVEN / SMOKER INITIAL START-UP
INSTALLATION & OPERATIONS MANUAL 1189200 REV 0 (12/06) PAGE 7 OF 24
F. Install the water supply if your unit was ordered with the optional AUTOMIST feature (refer to
WATER SUPPLY CONNECTION on the following page).
G. The installing technician or electrician should complete the electrical connections by
removing the Outside Top of the unit (this panel is pressed onto the top of the unit and
should lift off easily). Connect the unit to the available power supply either through an
attached cord and receptacle or through direct wiring by following these steps:
1.Take note of the labeling on the Power Terminal Block (Line 1, Line 2, Line 3, ).
2.Carefully identify the power source leads and attach them to the appropriate terminal
connections. Make sure all connections are clean and tight.
3.Properly ground the unit BEFORE USE by attaching a grounding wire to the Ground Lug
or Clamp provided next to the Power Terminal Block.
4.Allow enough slack in the wiring to allow for equipment to be moved about during
installation and any future servicing.
H. Check the voltage at the terminals on the Power Terminal Block with a voltmeter and
compare the values with the label listings on the side of the Oven. If the values match the
unit is ready for its INITIAL START–UP. If the readings DO NOT coincide you must call the
Southbend Service Department for instructions on changing the voltage and/or the phase.
I. Carefully position the Outside Top on the unit but do not press it into place. Position the unit
in its final operating location and refer to the appropriate INITIAL START–UP PROCEDURE
for your Smoker.
ELECTRICAL CONNECTIONS