10
Figure 13. Sanitizing Hopper
Figure 14. Spigot Opened and Solution Draining
D. Clean sides of hopper, mix inlet regulator and under-
side of hopper cover using a sanitized soft bristle
brush dipped in the sanitizing solution (Fig. 13).
3.4 FREEZE DOWN AND OPERATION
This section covers the recommended operating proce-
dures to be followed for the safe operation of the
freezer.
A. Sanitize just prior to use.
B. Place the OFF-ON switch in the OFF position.
C. With spigots open, pour approximately 1 gallon (3.8
liters) of mix into the hopper. Allow the mix to flush
out about 8 ounces (0.23 liters) of sanitizing solution
and liquid mix. Close the spigot.
D. Fill hopper with approximately 3 gallons (11.4 liters)
of prechilled (40°F or 4°C) mix.
NOTE
Do not overfill the hopper. Mix level must not be higher
than 2 inches (5 cm) from the top of the air inlet tube on
the mix inlet regulator.
E. The freezer barrel will automatically fill until it is
about 1/2 full. If freezer barrel does not fill, check for
obstruction in the mix inlet regulator. If freezer barrel
fills over 1/2 full, indicated by low overrun, check for
leaks at the mix inlet regulator O-ring or check if
the mix inlet regulator was installed correctly or that
the freezer is level.
F. Place the OFF-ON switch in the ON position, then
press the PUSH TO FREEZE swtich until the freezer
starts.
NOTE
After the auger drive motor starts, there is a 3
second delay before the compressor starts.
E. After five minutes, place a bucket under the spigot
and open spigot to drain sanitizing solution. When
solution has drained, press the CLEAN snap switch
to stop the auger. Allow the freezer barrel to drain
completely (Fig. 14).
F. Fill a tall cup with sanitizing solution. Completely
immerse the blender's agitator shaft in the sanitizer
solution. Do not wipe dry (Fig. 15).
Figure 15. Sanitizing Agitator Shaft