Fig. 7. Floor Stand
2.4 FLOOR STAND INSTALLATION
To install the E/F131G on the floor stand, follow the
steps outlined below.
1. Uncrate the floor stand and place in an upright posi
tion.
NOTE
Detailed instructions are included with each floor stand.
2. Place a spirit level across the top of the stand to
check for level condition, side to side and front to
back. If adjustment is necessary, level the stand by
turning the bottom part of each caster in or out, then
tighten the lock nut, and lock caster.
3. Remove the four legs from the freezer and replace
with the four leg adapters provided. Adapters must be
fully tightened to the freezer.
4. Place the E/F131G freezer on the floor stand with the
front of the freezer to the door end of the stand.
Secure the freezer to the stand with the nuts and lock
washers provided. Then separate freezer base gsaket
and install the seam to the back and the flat to the
bottom (Fig. 7).
2.5 INSTALLING PERMANENT WIRING
WARNING
ELECTRICAL TECHNICIANS MUST BE CONTINUOUSLY
ALERT TO THE PRACTICE OF ALL NECESSARY SAFETY
RULES AND PRECAUTIONS WHEN SERVICING THIS
EQUIPMENT AS VOLTAGES ARE PRESENT WHICH
CAN CAUSE SERIOUS OR FATAL INJURY.
ELECTRICAL WIRING MATERIALS, ARRANGEMENT
AND GROUNDING MUST CONFORM WITH NATIONAL
AND OTHER APPLICABLE ELECTRICAL CODES.
If permanent wiring is required by local codes, the following
procedure must be performed:
A. Remove the back panel.
B. Disconnect the wires from the terminal block. Discon-
nect the green ground wire from the grounding stud.
C. Remove the power cord.
D. Install permanent wiring according to local code.
E. Replace the back panel.
Figure 8. Power Cord Connection