3. Installation / Operation
The technician in charge of installation
must carefully read this manual before
operation of the machine, which must
be carried out by qualified staff, yet
respecting safety regulations in force.
The grinder must be installed in a flat
and stable surface, at a height which
makes operation of the machine
comfortable and safe, as close as
possible to the coffee machine.
The machine operator must be a
responsible adult person.
Electrical installation
Before connecting the grinder to the
mains, be sure of checking that the
grinder specifications correspond with
those of the power supply.
It is not recommended to use cord
extensions nor multiple connectors.
I.1 / I.2 / steel / i·mini /
i·steel machine Models
operation
Assemble the coffee bean hopper
3
on its position.
Fill it with coffee beans in such an
amount as to be consumed on a daily
basis. Put the hopper lid
2
on its
position.
Connect the power cord
7
to the
mains.
Push the ON-OFF switch
1
to turn
the machine on. The built-in led will
be on. The grinder will then be ready
for grinding.
Only models with a timer device (NO
USA), allows the operator to adjust
in advance the grinding time (a mini-
mum of 8 seconds and a maximum
of 60 seconds) by using regulator
6
. Every time ground coffee is required,
the machine filter holder must be
placed under the coffee spout
8
and
guided by the switch holder fork
9
,
pressing the switch
10
.
Turning the timer regulator
6
clockwise will result in an increase
of grinding time, whereas turning it
counterclockwise decreases grinding
time.(FIG.1)