Carrier 16DF013-050 Water Dispenser User Manual


 
Table 2 Overall Dimensions, 16DF013-025
English
UNIT
16DF
OVERALL DIMENSIONS (ft-in.)
013 015 018 020 023 025
LENGTH 11-10 11-10 11-10 11-10 11-10 11-10
WIDTH 6- 7 6- 7 7- 8 7- 8 8- 3 8- 3
HEIGHT 7- 9 7- 9 7- 9 7- 9 8- 3 8- 3
SI
UNIT
16DF
OVERALL DIMENSIONS (mm)
013 015 018 020 023 025
LENGTH 3600 3600 3600 3600 3600 3600
WIDTH 1995 1995 2330 2330 2520 2520
HEIGHT 2350 2350 2350 2350 2500 2500
Table 3 Overall Dimensions, 16DF028-050
English
UNIT
16DF
OVERALL DIMENSIONS (ft-in.)
028 032 036 040 045 050
LENGTH 15-4 15-4 15- 4 15- 4 15-4 15-4
WIDTH 9-4 9-4 9-10 9-10 10-6 10-6
HEIGHT 8-6 8-6 8-10 8-10 9-8 9-8
SI
UNIT
16DF
OVERALL DIMENSIONS (mm)
028 032 036 040 045 050
LENGTH 4660 4660 4660 4660 4660 4660
WIDTH 2850 2850 3000 3000 3200 3200
HEIGHT 2595 2595 2695 2695 2950 2950
RIGGING — The 2 pieces are the high-temperature generator-
separator assembly and absorber-evaporator low-temperature
generator assembly (Fig. 6).
1. Lift each assembly with cable, hooks, and shackles con-
nected to the 4 lifting holes on each assembly. Lifting
from other holes or locations can damage the machine.
2. Position and level the absorber-evaporator-assembly first.
See Position and Level the Equipment section.
3. Move the generator-separator assembly into place beside
the absorber-evaporator assembly.
4. Align connecting piping for generator-separator and absorber-
evaporator assemblies. Make sure serial numbers corre-
spond on both assemblies.
5. See Mounting the Burner section for burner rigging
instructions.
Position and Level the Equipment Isolation
pads are not necessary for most installations. However, for
cases where isolation pads are required, refer to Fig. 7 for
typical installation.
Both 16DF machine assemblies must be level within
1
4
in. per 20 ft (6.3 mm per 6 m), both lengthwise and di-
agonally. To level the machine, proceed as follows:
1. Completely fill 50-ft (15 m) length of clear flexible tub-
ing with water.
2. Use water gage and leveling reference points stamped on
tube sheets to level machine.
3. Level machine with shims until requirements are met. If
isolation assembly is used, shim under the soleplate. Be
sure matching piping is in alignment.
High-Temperature Generator-Separator Assembly
Fig. 6 — Rigging 2-Piece Units, Sizes 16DF023-050
Absorber-Evaporator Low-Temperature Generator Assembly
NOTES:
1. Be sure only the machine base is on the isolation pad at each
corner.
2. Shim under soleplate to level machine.
Fig.7—Typical Isolation Assembly
6