Figure 26. Ceiling Firestop (Ceiling Side)
If the area above the ceiling IS an attic, position and secure
the firestop on top of the previously framed hole.
NOTE: Keep insulation away from the vent pipe at least
1 inch (25mm).
Figure 27. Attic Firestop
JOIST
CEILING FIRESTOP
CEILING
NAILS (4 REQUIRED)
CEILING
CEILING FIRESTOP
RAFTER
NAILS (4 REQUIRED)
NOTE: There must be NO INSULATION or other
combustibles inside the framed firestop opening.
Figure 28. Trapezoid Termination Cap
7 1/4”
(184mm)
!
C. Vent Termination
Refer to Cinch Pipe and Termination Cap installation in-
structions.
Horizontal Termination
The termination kit should pass through the wall firestops
from the exterior of the building.
Adjust the termination cap to its final exterior position
on the building and interlock the flue sections.
!
WARNING: VENTING TERMINALS SHALL
NOT BE RECESSED INTO A WALL OR SID-
ING. VENT TERMINATION CLEARANCES MUST
BE FOLLOWED TO AVOID FIRE DANGER. SEE
VENT TERMINATION MINIMUM CLEARANCES DI-
AGRAM ON FOLLOWING PAGE.
WARNING: THE TERMINATION CAP MUST BE
POSITIONED SO THAT THE ARROW IS POINT-
ING UP.