Hearth and Home Technologies BH 105 Egg Cooker User Manual


 
Design:
The rst thing that needs to be done is deciding where and
how the boiler will be installed.
Things that need to be taken into consideration are the
intended use of the boiler for example, is the boiler going to
be used as your primary heating system or is it going to be
used as a secondary or backup heating system. If it is to be
used in conjunction with an existing oil or gas boiler system
will it be piped in parallel or in series? The answers to these
and other questions can be determined by talking to your
certied dealer or a qualied HVAC or plumbing contrac-
tor. This will ensure that the boiler is installed and piped to
accommodate your needs and expectations.
Consideration must be given to the venting as well as
electrical and clearance requirements. (Clearances must be
maintained to combustibles and also for service)
Make sure fans are not used in the fuel storage area, unless
they are installed so as not to create a negative pressure in the
room where the solid fuel burning appliance is located.
Refer to the illustration on page 3 to identify the compo-
nents listed below:
1. Install the control board cover as well as the access cover
located on the feeder cover.
2. Install the spring handles provided with the unit on the
ash door, rebox door and the heat exchanger cleanout rod
handles. (Fasten handles by turning them counterclockwise
and pushing inward simultaneously).
3. Install 3/4” MPT boiler drain in the tting as shown.
Note: Use pipe thread sealant or teon tape on ALL
threads before connections are made.
4. Install 3/4” MPT pressure relief valve as shown.
5. Install the 1/2” MPT aquastat well in tting as shown,
then place aquastat in the well and fasten with a zip tie. The
aquastat sensor is located under the top sheet metal jacket.
6. Install the 1/2” MPT temperature/pressure gauge in
tting as shown.
7. Locate and install outside air temperature sensor. Loca-
tion of this sensor should be on the north side of the home or
building and out of direct sunlight. Use the cable supplied
with the boiler to attach the sensor to the terminals located
on the hopper. (Place at the back side just above and to the
right of the main power connection box) The wires can be
connected to the sensor with the connectors supplied. Wire
nut or butt splice connectors could also be used. The con-
nections at the boiler can be done with the two 1/4” female
push on connectors supplied.
8. Fasten the conduit to the ash base with the clamps
provided.

Floor Protection:
The striped area indicates the minimum required oor protec-
tion area if the boiler is going to be placed on a combustible
oor. It requires 40” X 55”(US) or 42” X 55”(CAN) of non
combustible oor protection as shown. 16”(US) or 18”(CAN)
of the oor protection must be in front of the rebox door
as shown. Floor protection must be a minimum of 26 gauge
sheet metal. Floor protection must also be provided under any
horizontal run of vent pipe equal to the outside diameter of the
venting plus 2” to each side.
Example: 4” type “L” or “PL” vent pipe has an outside diam-
eter of 4-1/2” + 2” on each side equals a protected oor area
of 8-1/2” wide underneath the horizontal run.
42" CANADA
18" CAN
16" USA
40" USA
55" USA & CAN
MINIMUM NON-COMBUSTIBLE FLOOR PROTECTION AREA
NON-COMBUSTIBLE
FLOOR PROTECTOR
55" USA & CAN
42" CANADA
40" USA