28
Installation Guide ____________
; Unpack and Place MD-1000LT
1. Compare the dishwasher and site utility connections.
2. Level the dishwasher by adjusting the bullet feet.
3. Raise the doors and check the door clearance to the ceiling.
4. Move the dishwasher to its permanent location.
Utility Connections - MD-1000LT
Power: 115VAC 15Amp circuit
Water supply: 3/4" NPT hot water supply (140°F/60°C minimum)
(35 psi/241 KPa static pressure) 7-10 psi/63-69Kpa flow pressure
Drain: 1-7/8" stainless steel, slip-fit hose connection
Max flow: 15 Us gal/min. (13.5 Imperial gal/min) 57liters/min.
Chemicals: Detergent, rinse-aid, and sanitzer pumps are standard equipment.
Chemicals supplied by a chemical supplier
Chemical Dispensing Pumps - Factory Installed for MD-1000LT
• All pumps use liquid chemicals
• Detergent pump capacity = 350cc/min @ 108 RPM
Factory setting for detergent = 105cc in 18secs.
• Rinse-aid pump capacity = 35cc/min @ 14RPM
Factory setting for rinse-aid 14cc in 23 sec.
• Sanitizer pump capacity = 35cc/min @ 14RPM
Factory setting for Sanitizer= 14cc in 23 sec.
maintains 50PPM concentration of
5.25% sodium hypochlorite during
the final rinse cycle.
Note:
Installers must follow applicable sanitation, safety, plumbing, and electrical codes and
regulations; and work in accordance with best practices for dishwasher installation.