INSTALLATION
7
Completing Installation
1. Remove any foreign material from inside the machine.
2. Check to assure scrap basket and sump cover are in place.
3. After plumbing and electrical connections are completed, check the machine for water leaks
by depressing the
ON/FILL switch on the front panel, then close and latch the door(s). This
allows the tank to fill and to complete the rinse cycle. Check for leaks.
4. Open the door and check the water level. Water level should be at bottom of scrap screen.
5. Depress the
OFF/DRAIN switch, close door, push start switch to drain the tank. This allows
the machine to complete the wash and drain cycle. Check the drain plumbing for leaks.
6. Installation is now complete.
Front Side
of Tank
Indicates where proper
water level should appear
in the inlet chute area.