MODEL EZ-3 & EZ-5 COUNTERTOP STEAMERS INSTALLATION
OPERATOR’S MANUAL 1178387 REV 2 PAGE 7
INSTALLATION
Step 2: Electric Connection
A field connection Fuse Block is located at the rear of the unit, lower left side. A hole is provided for a 3/4”
conduit fitting (solid or flex). Rear cover and fuse block cover must be removed to gain access to fuse block.
Refer to Figure 2.
Be sure that the input voltage matches the requirement on the serial plate. The unit is factory wired per
customer order.
! WARNING
A POSITIVE GROUND CONNECTION IS ESSENTIAL. DO NOT ALLOW ANY TAMPERING OR
ADJUSTMENT OF ANY CONTROL OR WIRING. THE UNIT IS FACTORY SET. ADJUSTING ANY
INTERNAL COMPONENT OTHER THAN THE MAIN FUSE BLOCK CAN VOID THE WARRANTY.
THIS UNIT REQUIRES A KIT TO BE FIELD CONVERTED FROM THREE-PHASE TO SINGLE-
PHASE OR VICE-VERSA. CONSULT FACTORY FOR PHASE CHANGES.
All 208-220-240 and 480 volt units will have three fuse block sections, “L1-L2-L3”, for use with either 3-wire
3-phase or 2-wire, single-phase, 50 or 60 Hz. All 380V and 415V units will have four fuse block sections, “L1-
L2-L3-N,” for use with European style 4-wire 3-phase with neutral.
Figure 2
Rear Cover
Fuse Block Cover
(shown removed)
Fuse Block
3/4" Conduit
Fitting Hole
Serial
Plate