BREW VOLUME SET-UP: Use the following steps when the setting is unknown or a different circuit board is being
installed.
1. Place an empty funnel in the funnel rails and an empty decanter/server or graduated vessel beneath the funnel.
2. Place the "ON/OFF" switch in the "ON", upper position.
3. Press and hold the brew start button until you hear the brew solenoid click on-and-off three times
(approximately 5 seconds). Release the button.
4. Allow the cycle to continue until the desired amount of water is dispensed and then turn "OFF" the brewer.
The brewer is now set to dispense this amount of water for each subsequent brew cycle.
To increase the amount of water for each brew cycle place an empty funnel in the funnel rails and an empty
decanter/server or graduated vessel beneath the funnel. Press the "ON/OFF" switch. Press and hold the "BREW"
switch until you hear the solenoid click on-and-off three times (approximately 5 seconds), then release the "BREW"
switch. Momentarily press and release the "BREW" switch once for each ounce (approximate) of water to be added
to the prior setting and allow the brew cycle to finish.
To decrease the amount of water for each brew cycle place an empty funnel in the funnel rails and an empty
decanter/server or graduated vessel beneath the funnel. Press the "ON/OFF" switch. Momentarily press and
release the "BREW" switch once for each ounce (approximate) of water to be removed from the existing setting.
Press and hold the "BREW" switch until you hear the solenoid click on-and-off three times (approximately 5
seconds), then release the "BREW" switch and allow the cycle to finish.
ADJUSTMENTS & OPTIONAL SETTINGS (cont.)
29079 020103