INSTALLATION
Step 3: Electric Connection
A field connection Fuse Block is located at the rear of the unit, lower left side when facing the back of the unit
(see Figure 4 below). A hole is provided for a 3/4" conduit fitting (solid or flex). The rear cover must be
removed to gain access to fuse block (see Figure 9 on page 26).
Be sure that the input voltage matches the requirement on the serial plate. The unit is factory wired per
customer order.
! WARNING
A POSITIVE GROUND CONNECTION IS ESSENTIAL. DO NOT ALLOW ANY TAMPERING OR
ADJUSTMENT OF ANY CONTROL OR WIRING. THE UNIT IS FACTORY SET. ADJUSTING ANY
INTERNAL COMPONENT OTHER THAN THE MAIN FUSE BLOCK CAN VOID THE WARRANTY.
THIS UNIT REQUIRES A KIT TO BE FIELD CONVERTED FROM THREE-PHASE TO SINGLE-
PHASE OR VICE-VERSA. CONSULT FACTORY FOR PHASE CHANGES.
All 208-220-240 and 480 volt units will have three fuse block sections, “L1-L2-L3”, for use with either 3-wire
3-phase or 2-wire, single-phase, 50 or 60 Hz.
Figure 4
REAR VIEW
Water Drain
Water Inlet
Electric Connection