10. Remove remaining steam outlet elbow plumbing
from steam generator tank.
11. Remove delime hose from water level probe
assembly.
12. Remove hose from the vacuum relief solenoid.
13. Note wiring connection points and remove the
electrical wires from the VACUUM RELIEF
SOLENOID, WATER LEVEL PROBES and
PRESSURE SWITCH.
NOTE: Install a new gasket when reassembling
steam generator tank. Temporarily secure gasket in
place with RTV109.
14. Remove gasket from steam generator tank.
A. Clean remaining sealant from top lip of
steam generator tank.
15. Remove hardware securing steam generator
tank to machine frame (three places) then
remove tank from machine.
16. Remove water level probe assembly from tank.
17. If removed or replacing generator tank, install
insulation around generator tank. Secure into
position using high temperature aluminum foil
tape.
18. Reinstall parts removed in reverse order of
removal. Apply liquid thread sealant to all pipe
threads connected to the steam generator tank.
Do not apply thread sealant to fill union fitting.
19. Torque heating element screws to 70 in*lb
following the heating element tightening
sequence as found under HEATING ELEMENT.
20. Check steamer for proper operation. Inspect
inlets/outlets and gasket seal of steam