Installation
6
Oven Assembly
VENTILATION
1. Assemble the back vents.
2. Screw the back vent to the rear of each oven
section with the offset (enlarged) end toward
the bottom. Holes are provided. For stacked
units, the top of the lower back vent fits inside
the bottom of the upper vent.
3. Secure the trim to the top right of the upper
oven. The flanges on the right side, back and
front of the trim collar fit under the crown.
Use three sheet metal screws to attach the left
side of the trim to the top of the oven body
4. Remove all tags.
Figure 4
ULTRA R OKITE DECKS
Use only Blodgett Ultra Rokite Decks. Use of
decks other than Blodgett will invalidate the
warranty.
NOTE: Ultra Rokite shelves are heavy be careful
when handling.
1. Slide 1/2 of the Ultra Rokite shelf through the
door until it rests on the deflector. Move the
shelf to the rear until it drops into the shelf sup -
port. Push to the right.
2. Slide the remaining shelf through the door un-
til it rests on top of the other half. Move the
shelf to the rear untilit drops the shelf support.
Push all the way to the left.
3. Move both shelves in so the center joint
closes.
4. Level with shims provided if necessary.
5. Refer to preheating instructions supplied with
shelf.
ELECTRICAL CONNECTION
Before making any electrical connections to this
unit check the rating plate to be sure that the oven
is being connected to the proper electrical supply.
The supply conduit is connected to the right rear
of each oven section.
1. Remove the trim cover on the right lower front
of the oven to access t h e supply connecting
terminals.
2. Run the supply wires through the conduit t o
the front of the oven.
3. Connect the supply wires to the circuitbreaker
on the lower right front corner of the control
panel.
NOTE: When using an interconnection kit, refer to