Initial Start Up
Now that the brewer is connected, it can be started and checked.
• Leave the access cover open.
• Turn on the water supply.
• Turn on the electricity to the urn.
The urn will now begin to fill. The heaters should still be off. When the water level is above
the heaters, the contactor will close to turn on the heaters.
Check for leaks in the water connection and inside the control enclosure. Assuming all is
working correctly, close the control enclosure and allow to finish filling. An indicator light
labeled FILLING is lit while the fill valve is open. When the light turns off, the urn is full.
The urn will take approximately 15 minutes to fill.
If cold water is used, the heat-up time is approximately 30 minutes depending on the
electric ratings of the urn. An indicator light labeled WATER HOT will turn on when the
heaters have shut off.