Shipment Transit
1. The freezer has been operated and tested at the factory. Upon arrival the complete freezer
must be thoroughly checked for any damage which may have occurred in transit.
Note: A Tip (N) Tell warning device is placed on each shipping carton at the factory. If the
indicator is red, the carton has been tipped in transit. (See Figure B)
2. THE CARRIER IS RESPONSIBLE FOR ALL DAMAGE IN TRANSIT WHETHER VISIBLE OR
CONCEALED. DO NOT PAY THE FREIGHT BILL until the freezer has been checked for
damage. Have the carrier note any visible damage on the freight bill. If concealed damage
and/or shortages are found later, advise the carrier within 10 days and request inspection. The
customer must place any claim for damage and/or shortage with the carrier. Grindmaster
cannot make any claims against the carrier.
Inst
alling Y
our Unit
1. Place the self-sealing rubber pad (shipped with the freezer) on a level counter that is
stable and strong enough to safely support the freezer’s weight (245 lbs / 111 kg), or if
equipped with legs instead of pad, install legs by screwing them into the four leg holes
on the bottom of the unit. (Leg Kit Part # W0890220 (4) 4” Legs)
2. Make sure freezer is to be placed in a location that is within 6’ of a properly grounded
circuit and allows adequate space at each side and above for proper air circulation.
Air Cooled Units Only: Minimum clearance is 6” (15 cm) on both sides and 0” at back
and open above the freezer. (See Figure C)
NOTE: Failure to allow adequate ventilation will void the warranty and reduce
freezer performance.
NOTE: Locating the unit in high ambient temperatures (over 100°F / 37.8°C) will
significantly reduce the performance of your machine.
3. Remove the side panels and supporting all four sides, lift machine up (by the
frame) and place in appropriate area on top of rubber pad.
CAUTION: If equipped with spinner do not lift unit up by spinner shaft. It
will cause serious damage to spinner.
CAUTION: Beverage freezers are heavy pieces of equipment. It is
recommended that moving or lifting the unit be done by two people to
avoid injury.
4. The side panels should still be removed. Cut the cable tie on each motor used to secure
motor during shipment. Make sure motors rock freely. (Figure D)
5. 220V/50Hz Units: These units come with a plugless cord that requires the appropriate plug configuration be
connected. This must be determined by the power outlets at the specified location. See wiring diagram at back of
manual for assistance. It is recommended that a service technician performs this operation.
!
!
Figure B
Figure C
Figure D