HP (Hewlett-Packard) PS-025 Refrigerator User Manual


 
Page 8 PS QuarterHorse Series Chillers
1-4 Available Options
PS Series chillers are available with options that tailor the unit to your requirements.
Some are factory installed, some can be retrofitted in the field. Consult your local
Application Engineering Sales Representative. Some of these options are:
Power Cord
A 6 foot (1.8 m) power cord is available to speed PS installation.
Feet
Four leveling feet are mounted to the base of the PS unit.
1-5 Uncrating Your New Chiller
PS Series chillers are shipped mounted on a skid, enclosed in a plastic wrapper, and
open crated on all four sides and top.
; Pry the crating away from the skid and remove. Use a pry bar to remove the
blocks securing the unit to the skid.
; Lift the unit off the skid with a fork truck. Insert forks between skid and chiller
from the side until they protrude beyond the opposite side of the unit. The forks
must be equidistant from the center line of the unit and the unit must be balanced
on the forks.
; Lift slowly and only high enough to clear the skid. Use a pry bar if necessary to
remove the skid from the unit.
; Lower slowly. The unit will land on its feet or casters and can be moved into
position.