SV4.5 HT-2
Termination
SV4.5 HT-2
Termination
Horizontal terminations have been designed to perform in a wide range of
weather conditions. Our terminations meet or exceed industry standards.
When selecting the locations of your horizontal terminations, do not place the
termination where water from eaves and adjoining rooflines may create a heavy
flow of cascading water onto the termination cap. If the cap must be placed
where the possibility of cascading water exists, it is the responsibility of the
builder to direct the water away from the termination cap by using gutters or
other means.
Take care to carefully follow the installation instructions for the termination,
including the use of silicone caulking where required.
Figure 33
Figure 32 - INSTALLING SQUARE HORIZONTAL TERMINATION (SV4.5HT-2 or SF4.5HT-2)
Siding
Stucco
1-1/4” Maximum Recess of
Square Termination
into Exterior Finishing Material
Exterior Surface of
Framing
Exterior Surface of Siding
Maximum Extent of
Vent Run Sections
Relative to Exterior
Surface of Framing
Interior Surface of
Finished Wall
Last Vent Section.
Use Telescopic Vent
Section (SV4.5LA), If
Necessary
Adapter
SV4.5RCH
Use silicone caulking to seal
the top and sides of the
termination, up to the
underlayment, stucco, or
masonry wall surface.
Caulk
Caulk
Maximum Wall Thickness
10 in. (254 mm)
6 in. to 9-1/4 in.
(152 to 235 mm)
10¹⁄₂"
(267mm)
7"
(178)
5¹⁄₈"
(130 mm)
12¹⁄₈"
(308 mm)
Note: Centerline of Vent Piping is
NOT the Same as the Centerline of
the Framed Opening.
6 to 48 inch Vent Section,
Telescopic vent section,
Elbow or Appliance Collar
Base of Appliance
3"
(76 mm)
1"
(25.4 mm)
Adapter
SV4.5RCH
To help minimize water infiltration it is
recommended that the Firestop/Spacer
(SV4.5HF) be installed on the exterior
side of the wall.
Venting Connection and Exterior Wall Recessing of the Horizontal Square
Termination (SV4.5HT-2 or SF4.5HT-2).
See Figure 14 on Page 11 for Min.
Distance to Base of Appliance.
v
For thicknesses greater
than 10", see Table 12
SV4.5 HT-2
Termination
J. Assemble vent run to exterior wall - If not
previously measured, locate the center of the
vent at the exterior wall. Prepare an opening as
described in Step B. Assemble the vent system
to point where the terminus of the last section is
located relative to the exterior surface to which
the termination is to be attached (see Figures
32 & 33 and Table 12 on Page 21.
If the terminus of the last section is not within
this distance, use the telescopic vent section
SV4.5LA, as the last vent section. For wall thick-
nesses greater than that shown in Figure 33 on
Page 20 and Table 12 on Page 21. This table
lists the additional venting components needed
(in addition to the termination and adapter) for
a particular range of wall thicknesses.
K. Attach termination adapter - Attach the
adapter (adapter - SV4.5RCH - provided with the
termination) to the vent section or telescoping
vent section, elbow or appliance collar as shown
in Figures 32 & 33 in the same manner as any
SV4.5 vent component (refer to Step E).
L. Install Firestop/Spacer at exterior wall
- When using the square termination, install
SV4.5HF (Secure Vent), SF4.5HF (Secure Flex)
Firestop/Spacer over the opening at the exterior
side of the framing, long side up, with the 3 inch
spacer clearance at the top as shown in Figure
32, and nail into place.
(The Firestop/Spacer may also be installed over
the opening at the interior side of framing).
M. Install the Square Termination (SV4.5HT-2
or SF4.5HT-2)
Install the square termination - For the last step
, from outside the exterior wall, slide the collars
of the termination onto the adapter (the outer
inside the outer and the inner outside the inner)
until the termination seats against the exterior
wall surface to which it will be attached. Orient
the housing of the termination with the arrow
pointed upwards. Secure the termination to
the exterior wall. The horizontal termination
must not be recessed into the exterior wall
or siding by more than the 1-1/4" (32 mm) as
shown in Figure 33.
IMPORTANT
The vent termination is hot while
in operation and for a period of
time following the use of the fire-
place. To prevent contact with hot
surfaces, we recommend the use
of a Termination Guard. See Items
12 and 13 on Page 32. This can be
purchased at your local dealer.