Zanussi ZHC 590 Ventilation Hood User Manual


 
14
INSTALLING THE COOKER HOOD
Drilling the Ceiling/Support
Shelf
Use a plumb line to mark the centre of the hob on
the ceiling/support shelf.
Place the drilling template 21 provided on the ceiling/
support shelf, making sure that the template is in the
correct position by lining up the axes of the template
with those of the hob.
• Mark the centres of the holes in the template.
• Drill the holes at the points marked:
For concrete ceilings, drill for plugs appropriate to
the screw size.
• For hollow brick ceilings with wall thickness of 20
mm: drill ø 10 mm (immediately insert the Dowels
not provided).
For wooden beam ceilings, drill according to the
wood screws used.
• For wooden shelf, drill ø 7 mm.
• For the power supply cable feed, drill ø 10 mm.
For the air outlet (Ducted Version), drill according
to the diameter of the external air exhaust duct
connection.
Insert two screws of the following type, crossing them
and leaving 4-5 mm from the ceiling:
For concrete ceilings, use the appropriate plugs
for the screw size (not provided).
For Cavity ceiling with inner space, with wall thi-
ckness of approx. 20 mm, Screws not provided.
• For wooden beam ceilings, use 4 wood screws
(not provided).
For wooden shelf, use 4 screws with washers and
nuts (not provided)
Fixing the Frame
Unfasten the two screws fastening the upper chimney
stack 2.1 to the frame, and remove the chimney from
the upper stack.
If you wish to adjust the height of the frame, proceed
as follows:
Unfasten the four safety screws located at the top
in the frame separation area. (A)
• Unfasten the eight metric screws joining the two
columns, located at the sides of the frame. (B)
Adjust the frame to the height required, then replace
all the screws removed as above.
To guarantee greater stability in the frame, replace
the four safety screws in the last hole available.
Insert the upper chimney stack from above, and leave
it running free on the frame.
A
B