3. Top Coat Pump:
Turn on/off switch
ON.
Base Coat
Pump:
Tur n Pr ime
switch ON, or
activate applica-
tor switch on
material hose.
4. Rotate pressure
control knob 1/4
turn. Run pump
until a steady
stream of mate-
rial flows from
drain valve.
5. Turn on/off switch
OFF and turn
drain valve knob
to SPRAY.
6. Turn on/off switch
ON, and run
pump until a
steady stream of
material flows
from material
hose. Turn on/off
switch to OFF
and turn drain
valve knob to
DRAIN.
7. Connect applica-
tor to material
hose.
中文
3. 面漆泵:接通通
/ 断开关。
底色漆泵:接通
填料开关,或启
动料管上的喷涂
器开关。
4. 将压力控制旋钮
旋转 1/4 圈。让
泵运转,直到涂
料从泄压阀中平
稳地流出。
5. 关断通 / 断开
关,然后将泄压
阀旋钮旋转至喷
涂位置。
6. 接通通 / 断开
关,然后让泵运
转,直到涂料从
料管中平稳地流
出。关断通 /
开关,然后将泄
压阀旋钮旋转至
泄压位置。
7. 将喷涂器连接到
料管上。
ti10795b
ti11930a
ti10796b
ti13649a
ti13636a
ti13900a