Page 26 - 34003602EN/AB
XR11
XR11
2. Installation
Installation, connections
1 - Open the doors giving access to the
switch handles,
2 - Carry out the UPS shut-down procedure
and remove the three protective panels,
3 - Check:
◗ that the UPS is equipped with at least one
GTCZ communication card 17 and one
RAUZ card 18 .
◗ that a protected and UPS-secured outlet
19 is available.
4 - Configure the RAUZ and GTCZ card as
indicated in section 2.6.
5 - Connect the power supply adapter to the
UPS-secured outlet 19 . Bring the power
supply cord 20 out through the grommet in
panel A.
6 - Connect, install then fix link cable 21 .
Bring the other end of the cable out through
the grommet in panel A.
7 - Replace the protective panels.
2.9 Installing the PowerServices TelPac external unit for Galaxy UPSs
Installation must be carried out by our technicians.
Installation of the PowerServices TelPac external unit requires UPS shut down, load tranfer to bypass and removal
of three protective panels.
Refer to the UPS’s user manual to carry out shut-down procedures in full compliance with safety procedures and
instructions. Non-compliance with these may lead to safety hazards for the people concerned.
Galaxy view with doors open and protective panels removed
19
17
18
RAUZ card
red
black
brown
20
21