InRow RC Operation and Maintenance Manual4
Commissioning
After installation, complete the following checklists to verify that all components are working properly and that
the equipment is ready to begin operation.
Checklists
Initial inspection checklist
The initial inspection ensures that the equipment has been properly installed, the location of the cooling unit has
been properly prepared and the cooling unit is free of damage.
NOTE: The vapor barrier minimizes moisture infiltration. Without a vapor barrier, it will be difficult to maintain
the humidity in the room. Do not introduce unconditioned outside air into the space.
WARNING
DAMAGE TO EQUIPMENT OR PERSONNEL
Do not run service utilities in front of the fan outlet.
Failure to follow these instructions can result in death, serious injury, or
equipment damage.
Ensure that:
The installation procedure is complete according to the requirements of this installation manual.
The walls, floor, and ceiling of the room where the cooling unit is located are sealed with a vapor barrier.
There is no evidence of damage to the cooling unit.
The clearance around the equipment is in accordance with local and national codes and regulations as well
as this installation manual.
The cooling unit is level and joined to the adjacent racks
The cooling unit is not installed at the open end of a row.