OPERATION STRATOSTEAM COUNTERTOP STEAMER
PAGE 6 OF 44 OWNER’S MANUAL 1185184
ELECTRICAL REQUIREMENTS
One fused electrical connection is required to the contactor of each steamer. All steamers are shipped per customer
order, three phase or single phase. (A kit is available for field conversion to three phase or single phase.) The fused
connection must be wired for the required voltage and maximum amperage as listed in the chart below:
Voltage
Total Connected Amps
Model STRE-3EZ Model STRE-5EZ
1 Phase 3 Phase 1 Phase 3 Phase
208 V 60 Hz 44 26 53 31
220 V 50/60 Hz 41 24 51 29
240 V 60 Hz 38 22 46 27
WATER REQUIREMENTS
To meet warranty requirements, the water supply must be as follows:
Total Dissolved Solids (TDS) 60 PPM or less
Hardness 2 grains (35 PPM) or less
pH 7.0 to 7.5
Maximum Reservoir Capacity 3.0 gallons
Typical usage is 3.0 gallons in 4 hours.
In order to minimize service problems and to meet the warranty requirements, a water treatment system (softener) is
recommended when water quality does not meet the limits stated above.
DRAIN REQUIREMENTS
Water drains into a pan attached to the bottom of the steamer. Pan pulls out for periodic dumping.