— 4 —
C24EA SERIES ELECTRIC CONVECTION STEAMERS
LOCATION
Allow space for plumbing and electrical
connections. Minimum clearance is 6" (15.2 cm)
on the back for proper air circulation. Allow
adequate access for operating and servicing the
steamer: 36" (91.4 cm) at the front of the steamer,
15" (38 cm) above the steamer and 18" (45.7 cm)
on the right and left sides of the steamer.
LEVELING AND ANCHORING
Position the steamer in its final installed location.
Place a level on the horizontal area of the
cabinet. Adjust the feet to level the steamer in
both the left-to-right and front-to-rear directions.
Steamers should be elevated in the front just
enough, about
1
/16" to
1
/8" (2 to 3 mm), to
provide proper draining. Do this by rotating the
adjustable feet in the proper direction 1 to 1
1
/2
turns after leveling. Check drainage in the
steamer compartments by pouring a small
amount of water in the compartment. All the
water should drain.
The feet have holes in the flanges for anchor bolts.