Liebert 3000 Refrigerator User Manual


 
Installation
14
2.7.2 Ducted Applications
For ducted applications on units, the duct work may be attached to the top perimeter of the unit.
Refer to Figure 2 for information on upflow units and to Figure 3 for downflow units.
The duct work on upflow units must allow access to the motors/blowers for maintenance. The duct
work on upflow units must be designed within the capacity of the unit, otherwise air flow and perfor-
mance will be compromised.
2.7.3 Plenum Installation
A solid plenum or plenum with discharge grille(s) may be installed. The plenum and instructions for
its installation ship separately from the unit.
2.8 Checklist for Completed Installation
___ 1. Unpack and check received material.
___ 2. Proper clearance for service access has been maintained around the equipment.
___ 3. Equipment is level and mounting fasteners are tight.
___ 4. Piping completed to refrigerant or coolant loop (if required). Piping has been leak checked,
evacuated and charged (if required).
___ 5. Check piping within the unit & outside of the unit. Remove potential of rub-through or
chaffing.
___ 6. Condensate pump installed (if required).
___ 7. Drain line connected.
___ 8. Water supply line connected to humidifier (if required).
___ 9. Field provided pan with drain installed under all ceiling mounted fluid condensing units (if
installed).
___ 10. Filter box installed (if applicable).
___ 11. Ducting completed (if applicable).
___ 12. Filter(s) installed.
___ 13. Line voltage to power wiring matches equipment serial tag.
___ 14. Power wiring connections completed between disconnect switch, evaporator and condensing
unit, including earth ground.
___ 15. Power line circuit breakers or fuses have proper ratings for equipment installed.
___ 16. Control wiring connections completed to evaporator and condensing unit.
___ 17. Verify water detection is properly installed around all units (if installed).
___ 18. All wiring connections are tight.
___ 19. Control panel DIP switches set based on customer requirements.
___ 20. Foreign materails have been removed from, in and around all equipment installed (literature,
shipping materials, construction materials, tools, etc.).
___ 21. Fans and blowers rotate freely.
___ 22. Inspect all piping connections for leaks during initial operations. Correct as needed.
___ 23. Verify that a blank start-up sheet has been sent with the unit(s) and is ready to be completed
by the installer.