SECTION 2
INSTALLATION
9
SECTION 2
INSTALLATION
NOTE: The oven, when installed, must be electrically
grounded in accordance with local codes, or in the ab-
sence of local codes, with the National Electrical Code
(NEC), or ANSI/NFPA70.
NOTE
There must be adequate clearance between
the oven and any adjacent combustible con-
struction. Clearance must also be provided
for servicing and for operation.
CAUTION
It is required that the oven be placed under a
ventilation hood for adequate air supply and
ventilation.
CAUTION
Do not obstruct the flow of combustion and
ventilation air to and from your oven. Do not
obstruct the ventilation holes in the Control Panel.
CAUTION
On ovens with the Machinery Drive Compartment
located at the right end, a minimum clearance of
0″ to a left side wall, 18″ to a right side wall and 6″
from a back wall to air openings at the rear of the
oven must be maintained. On ovens with the
machinery/drive compartment located at the left
end, a minimum clearance of 0″ to a right side
wall, 18″ to a left side wall and 6″ from a back wall
to air openings at the rear of the oven must be
maintained.
For servicing and cleaning, a minimum of 18″
clearance from all walls is recommended.
I. UNLOADING
Your Middleby Marshall PS540-Series Oven is shipped
partially assembled. It will arrive in a carton on a crate.
Carton size for a PS540-Series Oven is:
84″ (2134mm) Long ×
58″ (1473mm) Wide ×
44″ (1118mm) High ×
The crate and carton must be examined before signing the
Bill of Lading. Report any visible damage to the transport
company, and check for the proper number of crates. If
apparent damage is found, make arrangements to file a
claim against the carrier. Surface Interstate Commerce
Regulations (U.S.A.) require that the claim must be
initiated by the consignee within 10 days from the date that
the shipment is received.
A Pre-installation Procedures Manual (MM P/N 88910-0009)
is attached to the exterior wall of the carton. This manual
contains detailed instructions on unpacking and moving the
oven(s) to the operating site. When the transport company
notifies you of an impending delivery, arrange to have a forklift
at your facility to unload the carton(s).
Instructions for stacking the ovens is continued in a
separate manual used by Middleby Marshall Authorized
Installers.
If you have a door wider than the carton, simply move the
carton into your facility and arrange an appointment with
your Middleby Marshall Authorized Installer.
If your door is narrower than the carton, then the oven will
have to be unpacked. Follow the directions shown in the
Pre-Installation Procedures Manual.