System Commissioning
This section of the manual is designed to be used with the
“Commissioning of Integrated Combo System” worksheet.
The worksheet is designed to guide you through the start-up
process in a logical, step by step method which should mini-
mize the work and time involved in having the system meet
the designed parameters.
The following conditions are assumed:
The air filter is in place
All supply diffusers and return grilles are fully open and
unrestricted
Hot water is available to the furnace
The drain valve for the heating loop is closed
The shut off valves for the heating loop are fully open
The throttling valve for the heating loop (if applicable), is
fully opened
Electrical power is available at the furnace
The return air temperature from the house is approxi-
mately 70°F (21°C)