Step 2
Install the beater assembly. First check s craper
blades for any nicks or signs of wear. If any nicks are
present or if the blade is worn, replace both blades.
Figure 5
If blades arein goodcondition, install thescraper blade
clip over the scraper blade. Place the rear scraper
blade over the rear holding pin (knife edge to the
outside). Holding the blade on the beater, turn it over
and install the front blade the same way.
Figure 6
Holding the blades in position, insert the beater
assembly into the freezing cylinder, and s lide the
assembly into position over the dr ive shaft. Turn the
beater slightly to be certain that the beater is properly
seated.
Figure 7
When in position, the beater will not protrude beyond
the front of the freezing cylinder.
Figure 8
Step 3
Install the torque rotor. Install the plastic guide
bearing on the short end of the torque rotor. Slide the
o- r ing into the groove on the long end of the torque
rotor and lubricate the o- r ing. Do not lubricate the
guide bearing.
Figure 9