Step 6
Install the handscrews on the studs. Tighten the
screws equally, using a criss- cross pattern. Do not
overtighten the handscrews.
Figure 19
Step 7
Install the torque arm. Position the torque arm by
inserting itthrough the slot inthe torqueswitch armand
down into the hole in the torque rotor which protrudes
from the door. Verify proper installation by moving the
torque rotor back and forth to be sure it moves freely
and easily.
Figure 20
Step 8
Install the front drip tray and splash shield. Install
the front dr ip tray and the splash shield under the door
spout.
Figure 21
Sanitizing
Step 1
Fill System. Disconnect the product supply linesfrom
the mix delivery container . Prepare a pail of approved
100 PPM sanitizing solution (examples: 2- 1/2 gal. [9.5
liters] of Kay- 5R or 2 gal. [7.6 liters] of
Stera- SheenR). USE WARM WATER ANDFOLLOW
THE MANUFACTURER’S SPECIFICATIONS. Pour
the solution into a clean, em pty mix delivery container.
Connect the container to the mix delivery line.