5
INITIAL SET-UP
NOTE: The LCC-2 (Chilled Unit) weighs approximately 80 lbs. (36.3 kg) and the LCA-2 (Ambient Unit) weighs
approximately 70 lbs. (31.8 kg). If necessary, use more than one person when lifting or moving the dispenser.
1. Locate and remove the information packets and tube kits from top of packaging and set aside.
2. Remove foam packing and cut around the bottom of box.
3. Remove the box and the rest of the foam packing.
4. Open the dispenser door and remove the drip tray and the lower splash guard panel.
5. Set dispenser on the counter where it is to be used. CAUTION:
DO NOT LIFT ON THE DOOR.
6. Confirm the dispenser is level on the counter.
ELECTRICAL HOOK-UP
CAUTION: Improper electrical installation will damage electronic components.
1. An electrician must provide electrical service as specified in conformance with all local, state and federal
electrical codes.
2. Using a voltmeter, check the voltage and color-coding of each conductor at the electrical source.
3. Connect the dispenser to the power source.
4. If plumbing is to be hooked up later, be sure the dispenser is disconnected from the power source. If plumbing
has been hooked up, the dispenser is ready for Initial Fill & Heat.
PLUMBING HOOK-UP
1. Install the 3/8" inlet flare fitting on the bottom right side of the dispenser.
2. Flush the water line to remove any debris or foreign material.
3. Securely attach the water line to the 3/8" flare fitting.
4. Turn on the water supply and check for leaks.
34766 112502