15
Model 220 Operating Procedures
080911
Step 7
Install the shelf. Choose the level desired and align
the grooves in the back of the shelf with the holding
collars. Slide the shelf down over the holding collars of
the same height on the left and right sides.
Figure 20
Sanitizing
Step 1
Preparea pailof approved100 PPM sanitizing solution
(examples: 2- 1/2 gal. [9.5 liters] of Kay- 5R or 2 gal.
[7.6 liters] of Stera- SheenR). USE WARM WATER
AND FOLLOW THE MANUFACTURER’SSPECIFIC-
ATIONS.
Figure 21
Step 2
Install the o- ring on the bottom o f the funnel.
Figure 22
Step 3
Lay the funnel and the hopper gasket in the bottom of
the mix hopper and pour the sanitizing solution into the
hopper.
Figure 23
Step 4
While the solution is flowing into the freezing cylinder,
brush clean the hopper and the mix inlet hole.
Figure 24