Fig. 8
2. Remove upper panel and pull out insulation cut-
away.
Fig. 9
3. Remove the racks from inside cavity.
4. Remove the probe guard.
Fig. 10
5. Remove probe by pushing it through the oven
wall and down through upper panel into the
control panel area.
Fig. 11
6. Reverse the procedure to install the replacement
probe.
7. Adjust the temperature control as outlined under
SOLID STATE TEMPERATURE CONTROL
CALIBRATION under Service Procedures and
Adjustments.
HEATING ELEMENTS
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
1. Remove RIGHT SIDE - REAR PANEL.
2. Disconnect element wire connectors.
VC3ED FULL SIZE ELECTRIC CONVECTION OVEN - REMOVAL AND REPLACEMENT PARTS
F45534 (0415) Page 8 of 31