Gravimetric Batch Blenders w/Mitsubishi Control Chapter 3: Installation 29
Machine Mount
In a machine mounting application of the Slide Gate/Auger unit, there are a few items to
review before placement and mounting of the blending system begins.
First, verify the machine flange dimensions match the Slide Gate blender flange (if the
optional pre-drilled holes were ordered). The Slide Gate blender can also be equipped with an
optional cast throat section with a drain port. This will bolt under the bottom plate of the
blender.
Verify that the machine throat is physically capable of supporting the Slide Gate/Auger
blending system with a full load of material and vacuum loading equipment installed.
Note: While in operation, the Slide Gate/Auger blender applies horizontal and
vertical pressures to the mounting flange. If there is a question as to the
mechanical stability of a mounting flange, contact the manufacturer’s
engineering department.
Verify all clearances on the top and beside the processing machine. This is to insure that all
motors, hoppers, control panels, etc. have adequate room for proper operation and servicing.
Refer to the assembly drawing with the unit for actual height and width dimensions.
Note: Allow at least 36” clearance around blender to provide adequate room for
cleaning, servicing, etc.
Using proper lifting equipment, lift the blender, using the lifting lugs attached to the top plate
of the blender. These lifting lugs can also be used to fasten horizontal or angled braces to the
blender if more stability is needed.
Take care to insure proper orientation with adequate access to operator controls, mix
chamber, and metering units.
Note: Never weld on the blender, support stand, machine or mezzanine without first
removing the control panel and verifying that the blender is properly grounded.