14
L. Electric Power Supply
TASK REFERENCE COMPLETED
Preparation Page No.
Make sure electric power requirements are met 1, 13
Check operating location clearances 3
Make sure location and exhaust hood requirements are met 5
Check field assembly of the 22CET 5
Check field assembly of stand (if used) 6, Separate
Instructions
Installation
Make sure 22CET is level 7
Check drain line connection 9
Check water supply connection 11
Leak test water supply lines 12
Check electrical line connection 13
Perform Operating Tests 15
2. Notes