hussman P/N 0420057_B Refrigerator User Manual


 
11. Re-apply caulk or silicone as required.
12. Verify glass is positioned and operating cor-
rectly.
JOINING INSTRUCTIONS
Sectional construction means that two or more
merchandisers may be joined in line yielding
one long continuous display requiring only one
pair of ends.
All joints must be air-tight to prevent formation
of ice or condensation.
Refer to the detailed information provided in the
separate Joining Instruction shipped with each
case.
INSTALLING COIL COVER AND
DRIP TRAY
Each gravity coil in these service merchandisers
has a 4 ft (1219 mm) stainless steel coil cover
and molded plastic drip tray. A condensate drip
tube is factory installed.
Check the drip tray for obvious damage before
installation. Damaged or leaking drip trays must
be replaced. Remove any loose debris and clean
the drip tray before installing.
Coil cover hooks and drip tray hooks are factory
installed at the front and back in each gravity
coil. Hanging holes are formed in the cover and
drip tray.
1-8 INSTALLATION
P/N 0420057_B
U.S. & Canada 1-800-922-1919 • Mexico 1-800-522-1900 • WWW.HUSSMANN.COM
Drip Tube
Connection
Coil Cover
Pivot Support
Adjusting Bolt
Set Screw
Positive Stop