EMC Departmental Switches DS-16M2 and DS-32M2 Installation Guide
Installing the DS-16M2 and DS-32M2 Switches
8. Install the bezel by positioning and installing the bezel stud
receptacles on the back of the bezel over the ball studs (39U rack)
or latch brackets (40U rack) on the rail ends.
9. Push the bezel onto the ball studs or latch brackets until it snaps
and locks into place. The illustration below shows an installed,
unpainted 16-port bezel in a 39U rack.
10. Plug one of the supplied power cords into each of the switch’s
two power receptacles.
11. When installing the DS-16M2 switch, run the power cords up in
front of the units and over the top of the uppermost switch.
Front View of 32-port Switch Installed in a 39U Rack
Rear View of 32-port Switch Installed in a 39U Rack