-53-
Revision 4/F3576 © Moffat Ltd, December 2004
1) Remove the stainless steel top cover from
the unit which is to become the bottom
unit.
2) Screw into place the insulation panel over
the fibre insulation (folded edge forward),
locating the rear slots of the panel with the
holes in the chassis member.
3) Drill two additional holes through the side
members to locate with the remaining two
holes in the insulation panel.
4) Locate and attach duct assembly onto top
of the bottom unit’s flue.
5) Unbolt the four legs of the base unit and
replace with the short legs supplied.
6) Remove the legs and leg frame from the
G1100 top unit.
7) Remove the back panel from the top unit.
8) Cut out slots in base panel of top unit for
chimney (refer figure A.2).
9) Insert and attach chimney assemblies with
2 screws each.
10) Fit side spacers and front cover to bottom
of top unit.
Figure A.2
APPENDIX A. DOUBLE STACKING INSTRUCTIONS
11) Stack the units, ensuring chimney and
duct are aligned and spacers line up with
holes in sides of bottom unit, and secure
with screws provided.
12) Attach rear spacer and re-fit the back
panel on the top unit
Figure A.1
Double Stacking Kit - part number 016393