Sterling A0567659 Blender User Manual


 
SGB Batch Blender with Mitsubishi Controller Page 45 of 118
4-7-4 Final Setup
1. Connect the blender to the appropriate power source.
2. Connect the compressed air piping, ensuring that a 5-micron air
filter is installed, along with the proper water trap, and lubrication
unit, if required. Verify that 60 psi (4.14 bar) of clean, dry
compressed air is supplied to the blender.
Important! Again, make sure that proper air supply connections are made to
the blender, as dirty, contaminated, wet air can damage blender
components and can quickly cause poor performance and
accuracy!
Make sure that the blender is supplied with clean, dry,
60 psi (4.14 bar) compressed air.
3. After powering up the blender the following screen will be shown:
This screen displays the software version of both the PLC and the
F940. The Controller will stay on this screen for about 4 seconds,
then enter the Recipe Screen (Next Screen in sequence). The
software versions are also available on the F940 Configuration
Screen.