Carrier PC211 Refrigerator User Manual


 
Initial Start-Up Checklist for 19XL Hermetic Centrifugal Liquid Chiller
(Print and use for job file)
Cutler-Hammer® Solid-State Starters
1.
Check that all wiring connections are properly terminated to the starter.
2.
Verify that the ground wire to the starter is installed properly and is of sufficient size.
3.
Verify that the motor is properly grounded to the starter.
4.
Check that all of the relays are properly seated in their sockets.
5.
Verify that the proper ac input voltage is brought into the starter. Refer to the certified
drawings.
The order in which the solid-state control module adjustment potentiometers are set is
Click here for Initial Start-Up Checklist for 19XL Hermetic Centrifugal Liquid Chiller
This equipment is at line voltage when ac power is connected. Pressing the STOP
button does not remove voltage. Use caution when adjusting the potentiometers
on the equipment.
WARNING
!
WARNING