5.5 Opening the Project
5 - 61
1
OVERVIEW
2
SYSTEM
CONFIGURATION
3
SPECIFICATIONS
4
SCREEN
CONFIGURATION
5
OPERATING
METHOD
6
FUNCTIONS
7
INTERNAL DEVICE
INTERFACE
FUNCTION
8
TROUBLESHOOTING
APPENDICES
5.5 Opening the Project
Set a project data for monitoring and start monitoring.
1 Perform either of the following operations.
• Click (Open a GT Designer2 file.).
• Select [Project] [Open] from the menu.
• Right-click the mouse and select [Open] from the menu.
2 The Open a GT Designer2 file. dialog box is displayed.
Set up the following items and click the button.
Item Description
Look in Selects the area where the project data is saved.
File name Sets project data name for monitoring.
Files of type
Selects a file format of the project data.
GT Designer2 file(*.gte) : GTE format
Open