6-5
Note
Purging allows sample gas to flow through the sample loop for 60 seconds prior to
beginning the first analysis.
4. Check the Continuous operation check box to set or unset repetitive
analysis. The checkbox is selected by default.
5. Click OK and the analysis starts. Use the Mode column on the GC
Status Bar to monitor the status of the analysis run.
Figure 6-7. The GC Status Bar
Note
To view the results of the Auto Sequence run, select Report Display from the Logs/
Reports menu.
6.4 Calibrating the gas chromatograph
Calibration runs are determined by the CDT and Streams settings. See
“Managing Component Data Tables” on page 4-5 and “Creating a stream
sequence for a detector” on page 4-78 for detailed instructions on how to
edit these settings.
To calibrate a GC, do the following:
1. Select Calibration... from the Control menu. The Start Calibration
window displays.