Emerson Process Management 3-9000-745 Wok User Manual


 
MON20/20 Software for Gas Chromatographs User Manual
SEPTEMBER 2010 3-9000-745
6-7
(b.) Select Forced to perform a manual calibration in which the CDT
for the selected stream(s) will be updated with calibration data
even if that data is outside the acceptable deviations, as listed on
the CDT. For more information, see “Managing Component Data
Tables” on page 4-5.
5. Click OK and the calibration starts. Use the Mode column on the GC
Status Bar to monitor the status of the operation.
Figure 6-9. The GC Status Bar
Note
To view the results of the Auto Sequence run, select Report Display from the Logs/
Reports menu.
6.5 Validating the Gas Chromatograph
During a validation run, the GC performs a test analysis to verify that it
is working properly. The test analysis is performed on a gas whose
component concentrations are already known; if the GC’s results deviate
significantly from the predetermined data, an alarm is generated.
Validation runs are determined by the validation data table and streams
settings. See “Managing Validation Data Tables” on page 4-35 and
“Creating a stream sequence for a detector” on page 4-78 for detailed
instructions on how to edit these settings.
To validate the GC, do the following:
1. Select Validation... from the Control menu. The Start Validation
window displays.